Stora Enso Oulu Oyj: Cardboard mill renovation phase 2 (new pipe bridges)
At Stora Enso’s board mill, the old paper machine was converted into a board machine. In this large O750 project, we modernised an old factory with the support of our subcontracting network.
At the workshop, we manufactured, fitted with pipes and insulated a total of 36 new pipe bridge modules, with a total length of 700 metres and a weight of approximately 750 tonnes.
We transported the modules by special transport to Oulu, where we lifted them into place and carried out connections to make the modules ready for operation.